North Campus HVAC Project Update

As reported earlier this month, Baruch College—in partnership with the Dormitory Authority of the State of New York (DASNY)—is working to upgrade the HVAC systems of the North Campus. An important piece of this $14 million capital project is replacing the cooling towers on the roofs of the Newman Vertical Campus (NVC) and the Information and Technology Building. These towers play a significant role in the maintenance of temperature.

Unfortunately, this work has been slightly delayed. Here is an update:

This past Saturday, Jan. 28, a street crane successfully removed the existing cooling towers of the Information and Technology Building (see image left). The downside of removal, however, is that there is no direct way to modulate the temperatures throughout the NVC and the Information and Technology Building while work is in progress.

Crane lifting temporary cooler in place

Be advised that campus engineers are doing their best to accommodate temperature-related complaints. The problem: When heat is reduced in one area, another area becomes even colder, and vice versa. Unfortunately, we anticipate that this situation will continue through this week, until the temporary chiller‒moved to accommodate the crane and other connections‒is back in operation.

Expected to be operational by Monday, Feb. 6, the temporary chiller will make it easier to modulate temperature. The first of the new cooling towers should be operational at the end of March or beginning of April, and the entire project is scheduled for completion this summer.

When completed, this upgrade will allow campus engineers to control the numerous components that balance the heating and air conditioning to the North Campus floors and rooms.

We apologize for any inconvenience and will continue to keep you apprised of developments.

Thank you for your patience and understanding.

Lisa Edwards
Assistant Vice President of Campus Facilities